1st quarter of 2015/2016
PROJECT MANAGER |
CONTRACT NO | DESCRIPTION OF BIDS AWARDED FOR THE MONTH OF JULY 2015 |
DATE SERVED AT BAC |
SUPPLIER |
April Dlamini | A-EE 17/2014 | Supply, install and maintain 2 x 250KWp rooftop solar PV power plants until 30 June 2017 | 23-Feb-15 |
Root 60 Four Energy (Pty) Ltd/Asunim Solar South Afric (Pty) Ltd |
Sibongile Shoba Liaane de Witt |
Paragraph 31 |
Procurement of related services for fibre optic network build – as and when – until 30 June 2017 – subject to contract amount or 30 June 2017 whichever comes first |
23-Mar-15 |
Bona Electronic Solutions (Pty) Ltd |
Vincent Willie | Section 110 |
Appointment of Telkom SA SOC LTD to render a managed internet service for a period not exceeding 36 months |
13-Apr-15 | Telkom SA SOC LTD |
Nerline Swanepoel | PS-RE 79/2014 |
Consulting teams consisting of a landscape architect whit professional teams to render full professional services – as and when for various park and cemetery development projects until 30 June 2017 |
21-May-15 |
Karien Hanekom Land Architects/Marian Louw Land Architects JV |
Nerline Swanepoel | PS-RE 79/2014 |
Consulting teams consisting of a landscape architect whit professional teams to render full professional services – as and when for various park and cemetery development projects until 30 June 2017 |
21-May-15 | Red Landscape Architects (PTy) Ltd |
Nerline Swanepoel | PS-RE 79/2014 |
Consulting teams consisting of a landscape architect whit professional teams to render full professional services – as and when for various park and cemetery development projects until 30 June 2017 |
21-May-15 | Outer Space JV |
Nerline Swanepoel | PS-RE 79/2014 |
Consulting teams consisting of a landscape architect whit professional teams to render full professional services – as and when for various park and cemetery development projects until 30 June 2017 |
21-May-15 |
Du toit Kusel landscape Arvhitects cc t/a Habitat Landscape Architects |
Ryk de Beer | PS-DEMS 32/2015 |
Appointment of architects and a professional team to render full professional services for the extension of the Farrarmere fire stations |
22-Jun-15 |
NON AWARD Fair admin process was not followed Accountability not signed |
Thuthuka Mathe | A-F 06/2015 | Appointment of qualified electricity disconnection contractors – as and when – from 1 July 2015 – 30 June 2018: South West Area: Germiston and Alberton | 22-Jun-15 | Explosion Crew and Projects (Pty) Ltd |
Thuthuka Mathe | A-F 06/2015 | Appointment of qualified electricity disconnection contractors – as and when – from 1 July 2015 – 30 June 2018 South West Area: Germiston and Alberton | 22-Jun-15 | Lilitha Engineering Solutions (Pty) Ltd |
Thuthuka Mathe | A-F 06/2015 | Appointment of qualified electricity disconnection contractors – as and when – from 1 July 2015 – 30 June 2018 South West Area: Germiston and Alberton | 22-Jun-15 | Thamar Investment (Pty) Ltd |
Thuthuka Mathe | A-F 06/2015 | Appointment of qualified electricity disconnection contractors – as and when – from 1 July 2015 – 30 June 2018 South West Area: Boksburg & Edenvale | 22-Jun-15 | Nala Trading Enterprise CC |
Thuthuka Mathe | A-F 06/2015 | Appointment of qualified electricity disconnection contractors – as and when – from 1 July 2015 – 30 June 2018 South West Area: Boksburg & Edenvale | 22-Jun-15 | Methorn CC |
Thuthuka Mathe | A-F 06/2015 | Appointment of qualified electricity disconnection contractors – as and when – from 1 July 2015 – 30 June 2018 South West Area: Boksburg & Edenvale | 22-Jun-15 | Magna Business Consulting (Pty Ltd |
Thuthuka Mathe | A-F 06/2015 | Appointment of qualified electricity disconnection contractors – as and when – from 1 July 2015 – 30 June 2018 North East Area: Tembisa Benoni & Kempton Park | 22-Jun-15 | Sekunjalo Rubble Cleaning CC |
Thuthuka Mathe | A-F 06/2015 | Appointment of qualified electricity disconnection contractors – as and when – from 1 July 2015 – 30 June 2018 North East Area: Tembisa Benoni & Kempton Park | 22-Jun-15 | African Meter Reading (Pty) Ltd |
Thuthuka Mathe | A-F 06/2015 | Appointment of qualified electricity disconnection contractors – as and when – from 1 July 2015 – 30 June 2018 North East Area: Tembisa Benoni & Kempton Park | 22-Jun-15 | Mokgoshi Electrical CC |
Thuthuka Mathe | A-F 06/2015 | Appointment of qualified electricity disconnection contractors – as and when – from 1 July 2015 – 30 June 2018 North East Area: Brakpan, Nigel & Springs | 22-Jun-15 | Themba & Ndlozi JV |
Thuthuka Mathe | A-F 06/2015 | Appointment of qualified electricity disconnection contractors – as and when – from 1 July 2015 – 30 June 2018 North East Area: Brakpan, Nigel & Springs | 22-Jun-15 | Yande Engineering and Projects CC |
Thuthuka Mathe | A-F 06/2015 | Appointment of qualified electricity disconnection contractors – as and when – from 1 July 2015 – 30 June 2018 North East Area: Brakpan, Nigel & Springs | 22-Jun-15 | Gohitile Projects Management CC |
Edwin Morulane | WS 03/2014 | Construction of Illiondale Outfall sewer | 22-Jun-15 | ZM and Nikiwenono Construction CC |
Johnny vd Merwe | A-EMPD 04/2015 | Supply, delivery and off-loading of animal feed and bedding for the EMPD – as and when until 30 June 2018 | 6-Jul-15 | Madi Ngalonde Trading CC |
Johnny vd Merwe | A-EMPD 04/2015 | Supply, delivery and off-loading of animal feed and bedding for the EMPD – as and when until 30 June 2018 | 6-Jul-15 | Milmac Feeds t/a Umzume Investments CC |
Mandla Ramotsheke |
ED 12/2014 | Supply, delivery, installation and commissioning of electric fencing at Springs Fresh Produce Market | 6-Jul-15 |
NON AWARD * No qualifying bidders |
Ryk de Beer | PS-DEMS 30/2015 |
Architects and a professional team to render a full professional service for the construction of a new fire station in Olifantsfontein |
13-Jul-15 | Anderson Vogt Consulting CC |
Ryk de Beer | PS-DEMS 37/2015 |
Architects and a professional team to render a full professional service for the restoration of the old Germiston Fire Station |
13-Jul-15 | Anderson Vogt Consulting CC |
Fumani Shirilele Karabo Ledwaba |
A-WMS 14/2014 |
REPORT BACK ON NEGOTIATIONS Appointment of a contractor of carry out routine maintenance of site infrastructure and ad-hoc post closure rehabilitation work at the Alberton North, Nigel, Southern dumping sites and closed Wadeville landfill sites – as and when until 30 June 2017 |
13-Jul-15 | Tsoga o Bune Building Enterprise CC |
Yusuf Mayet | Section 110 |
Appointment of supplier to provide exhibition space at the Gauteng Infrastructure Conference 16 – 17 July 2015 at Gallagher Estates |
13-Jul-15 | Gauteng Growth and Development Agency |
Busi Hlohlongoane | A-CL 02/2015 | Supply and delivery of NB2-M2 box bases and NL2/3-M2/3 box lids – as and when – until June 2017 | 20-Jul-15 | Metro Files (Pty) Ltd |
Vusi Qwabe Obed Nhlapo |
Paragraph 32 |
To utilize National Treasury Contract RT 57-2015: Supply and delivery of sedan vehicles, light and heavy commercial vehicles, busses and motor cycles 1 July 2015 – 31 March 2016 |
20-Jul-15 | Panel of suppliers |
Lydia Motlhale | A-HEA 01/2015 |
Packing, supply and delivery of nutritional food supplement to serve as an immune booster at the Primary Health Care Facilities – as and when until 30 June 2018 |
20-Jul-15 | Loira Medical Suppliers CC |
Lydia Motlhale | A-HEA 01/2015 |
Packing, supply and delivery of nutritional food supplement to serve as an immune booster at the Primary Health Care Facilities – as and when until 30 June 2018 |
20-Jul-15 | Extra-Dimension 1077 CC |
Arthur Zwane Ryk de Beer |
A-CRM 01/2015 |
Supply, delivery, installation, commissioning and maintenance of CCTV Surveillance cameras – as and when – until 30 June 2017 |
20-Jul-15 |
CANCELLED No qualifying bidders |
Moloko Mosohli | AS 05/2015 |
Withdrawal and subsequent award: Supply, delivery and off-loading of bond paper and/or Tokai Board and files – as and when – until 30 June 2016. |
27-Jul-15 | Mponiki Holdings (Pty) Ltd |
Moloko Mosohli | AS 05/2014 |
Withdrawal and subsequent award: Supply, delivery and off-loading of bond paper and/or Tokai Board and files – as and when – Subsequent award |
27-Jul-15 | Jabatha Paper and Stationery CC |
Moloko Mosohli | AS 05/2014 |
Withdrawal and subsequent award: Supply, delivery and off-loading of bond paper and/or Tokai Board and files – as and when – until 30 June 2016 |
27-Jul-15 | Integrity Environmental Solutions (Pty) Ltd |
Moloko Mosohli | AS 05/2014 |
Withdrawal and subsequent award: Supply, delivery and off-loading of bond paper and/or Tokai Board and files – as and when – until 30 June 2016 |
27-Jul-15 | Memotek Trading |
Jaco du Plooy | PS-RS 86/2014 |
Appointment of a professional transport planning firm to provide transport modeling services to review the existing 2013 EMM Road Master Plan and the transport model in EMME 4 and to do modelling of various sub-areas on a micro level until 30 June 2017 |
13-Jul-15 | Gibb (Pty) Ltd |
Mothebe Matooane |
PS-EPMO 08/2015 |
Appointment of specialist service providers to render professional services to support the successful implementation of flagship and capital projects – as and when – until 30 June 2017 Monthly reporting to be submitted to SCM |
29-Jun-15 | Panel of consultants |
Innocent Mulaudzi | EE 04/2014 | Construction of Mayfield switching stations A & B | 4-May-15 |
Tension Overhead Electrification (Pty) Ltd/ Uvuko Civils Maintenance and Construction JV |
Lebogan Montshonyane |
A-RS 04/2014 |
Supply and delivery of cement for various CCCs – as and when – until 30 June 2017 Northern and Southern SDA. |
8-Jun-15 | Nala Trading Enterprise CC |
Lebogan Montshonyane |
A-RS 04/2014 |
Supply and delivery of cement for various CCCs – as and when – until 30 June 2017 Eastern SDA |
8-Jun-15 |
KPJ Transport (Pty) Ltd |
Renier Cooper | A-RE 01/2015 |
General maintenance of the Cluster 2 cemeteries until 30 June 2017 Vlakfontein & Thokoza/Schoeman |
8-Jun-15 | Humelela Maintenance Services CC |
Renier Cooper | A-RE 01/2015 |
General maintenance of the Cluster 2 cemeteries until 30 June 2017 8th Avenue |
8-Jun-15 | Blue Lwandle Projects (Pty) Ltd |
Renier Cooper | A-RE 01/2015 |
General maintenance of the Cluster 2 cemeteries until 30 June 2017 Buyafuthi & Sasol |
8-Jun-15 | Mankoai Trading Enterprise CC |
Renier Cooper | A-RE 01/2015 |
General maintenance of the Cluster 2 cemeteries until 30 June 2017 Duduza New |
8-Jun-15 | Oritis Trading and Projects (Pty) Ltd |
Renier Cooper | A-RE 01/2015 |
General maintenance of the Cluster 2 cemeteries until 30 June 2017 Duduza Old & Tsakane |
8-Jun-15 | Lungibo Business Enterprise CC |
Renier Cooper | A-RE 01/2015 |
General maintenance of the Cluster 2 cemeteries until 30 June 2017 Duduza Unknown & Or Tambo |
8-Jun-15 | Dancehall Projects (Pty) Ltd |
Renier Cooper | A-RE 01/2015 |
General maintenance of the Cluster 2 cemeteries until 30 June 2017 Edenvale |
8-Jun-15 | Kamawa Trading Enterprise CC |
Renier Cooper | A-RE 01/2015 |
General maintenance of the Cluster 2 cemeteries until 30 June 2017 Kwa Thema 2 |
8-Jun-15 | Barry Buys (Pty) Ltd |
Renier Cooper | A-RE 01/2015 |
General maintenance of the Cluster 2 cemeteries until 30 June 2017 Magagula Heights |
8-Jun-15 | SJ Construction CC |
Renier Cooper | A-RE 01/2015 |
General maintenance of the Cluster 2 cemeteries until 30 June 2017 Mahimong |
8-Jun-15 | Just Design Landscaping & Maintenance CC |
Renier Cooper | A-RE 01/2015 |
General maintenance of the Cluster 2 cemeteries until 30 June 2017 Boksburg Old & Primrose |
8-Jun-15 | Boitlane Investments (Pty) Ltd |
Renier Cooper | A-RE 01/2015 |
General maintenance of the Cluster 2 cemeteries until 30 June 2017 Old Vosloorus |
8-Jun-15 | Tse Di Tlhaga Suplly and Projects |
Renier Cooper | A-RE 01/2015 |
General maintenance of the Cluster 2 cemeteries until 30 June 2017 Sebenza |
8-Jun-15 | Voisaan Projects CC |
Renier Cooper | A-RE 01/2015 |
General maintenance of the Cluster 2 cemeteries until 30 June 2017 Verwoerdpark |
8-Jun-15 | Goodwork Seciruty and Cleaning Services CC |
Renier Cooper | A-RE 01/2015 |
General maintenance of the Cluster 2 cemeteries until 30 June 2017 Vosloorus |
8-Jun-15 | Shihungasi Enter[prise and Social Consultancy CC |
Vincent Nkosi | A-WS 04/2015 |
Supply, delivery and off-loading and provision of temporary water through water tankers and stationary tanks within EMM – as and when – until 30 June 2017 |
4-May-15 | Samano Trading Projects CC |
Vincent Nkosi | A-WS 04/2015 |
Supply, delivery and off-loading and provision of temporary water through water tankers and stationary tanks within EMM – as and when – until 30 June 2017 |
4-May-15 | TCM Developments (Pty) Ltd |
Vincent Nkosi | A-WS 04/2015 |
Supply, delivery and off-loading and provision of temporary water through water tankers and stationary tanks within EMM – as and when – until 30 June 2017 |
4-May-15 | Polson Vervoer (Pty) Ltd |
Vincent Nkosi | A-WS 04/2015 |
Supply, delivery and off-loading and provision of temporary water through water tankers and stationary tanks within EMM – as and when – until 30 June 2017 |
4-May-15 | Anix Trading 567 CC |
Mabeane Matjokotja | A-EE 02/2014 |
Supply, delivery and off-loading of single and 3 phase split pre-paid meters (BS Footprint) as and when – until 30 June 2017 SUBJECT TO CAPPED AMOUNT OR 30 June 2017 whichever comes first |
13-Apr-15 | Landis and Gyr (Pty) Ltd |
Mabeane Matjokotja | A-EE 02/2014 |
Supply, delivery and off-loading of single and 3 phase split pre-paid meters (BS Footprint) as and when – until 30 June 2017 SUBJECT TO CAPPED AMOUNT OR 30 June 2017 whichever comes first |
13-Apr-15 |
Protection and Control a div of Actom (Pty) Ltd |
Kgaogelo Molema | A-F 03/2015 |
Appointment of a municipal valuer for the compilation of the valuation roll that will be valid for a four (4) year period w,e,f, 1 July 2017 – 30 June 2021 in compliance with the local government: Municipal Property Act 2004 (Act No 6 of 2004) – until 30 June 2018 |
3-Aug-15 |
Indigo Kulani Group (Pty) Ltd, Lutando Property Group (Pty) Ltd and A and Sons Property Group (Pty) Ltd Consortium |
Mike de Necker | A-F 07/2015 | Supply, delivery and off-loading of pay slips and attendance registers – as and when – until 30 June 2018 | 3-Aug-15 |
Tshilidzi Tshawe Construction, Suppliers, Transportation, Cleaning Services and More (Pty) Ltd |
Lebuile Mogakwe | A-HEA 05/2015 |
Collection, washing, ironing and folding of soiled laundry and the repairing of torn linen and delivery thereof back to Primary Health Care facilities – as and when until 30 June 2018 |
3-Aug-15 |
Dingwathe General Dealer (Pty) Ltd, subject to satisfactory due diligence by visting premessis |
Dikeledi Booysen | A-RE 02/2014 | Supply, delivery, off-loading and assembling of office furniture – as and when until 30 June 2017 | 3-Aug-15 |
NON AWARD Not complied with local content requirements of DTI |
Rodney Mohoto | A-HR 03/2014 |
Training services providers required for the implementation of all recognition of prior learning interventions for all departments – until 30 June 2017 |
17-Aug-15 | BC Landscape Training and Consultancy CC |
Rodney Mohoto | A-HR 03/2014 |
Training services providers required for the implementation of all recognition of prior learning interventions for all departments – until 30 June 2017 |
17-Aug-15 | Ngwato Wa Mphela Agricultural Training Services CC |
Rodney Mohoto | A-HR 03/2014 |
Training services providers required for the implementation of all recognition of prior learning interventions for all departments – until 30 June 2017 |
17-Aug-15 | Clean Heat Academy (Pty) Ltd |
Rodney Mohoto | A-HR 03/2014 |
Training services providers required for the implementation of all recognition of prior learning interventions for all departments – until 30 June 2017 |
17-Aug-15 | BH Trining and Consulting (Pty) Ltd |
Rodney Mohoto | A-HR 03/2014 |
Training services providers required for the implementation of all recognition of prior learning interventions for all departments – until 30 June 2017 |
17-Aug-15 | PWI Corporate Training (Pty) Ltd |
Rodney Mohoto | A-HR 03/2014 |
Training services providers required for the implementation of all recognition of prior learning interventions for all departments – until 30 June 2017 |
17-Aug-15 | Tipp Solutions CC |
Maropeng Raphela | PS-SRAC 28/2015 |
Architect as principal agent with a consulting team to render full professional services for the design and development of a community recreational pool in Duduza Value to be determined using final value of the contract |
17-Aug-15 | ZAS Atchitects and Planners CC |
Moloko Mosohli | AS 05/2014 |
Withdrawal and subsequent award Supply, delivery and off-loading of bond paper and/or Tokai Board and files – as and when – until 30 June 2016> Bidder did not accept award |
17-Aug-15 | Thumncu (Pty) Ltd (Withdrawn) |
Moloko Mosohli | AS 05/2014 |
Withdrawal and subsequent award Supply, delivery and off-loading of bond paper and/or Tokai Board and files – as and when – until 30 June 2016 Bidder did not accept offer – awarded to Shosho Industrial supplies |
17-Aug-15 | Shosho Industrial Supplies CC |
Johann Hatting | A-RS (R ) 04/2013 | Supply, delivery and off-loading of various types of pre-cast concrete kerbs – as and when until 30 June 2015 | 17-Aug-15 |
NON AWARD Validiy period expired |
Nditsheni Netshiluvhi | A-WS 16/2015 | Contractors for the replacement of aged domestic water meters – as and when until 30 June 2018\ | 17-Aug-15 |
CANCELLATION Fair admin process not followed |
Evelyn Phokwane | WS 05/2014 | Construction of a pump station in Eden Park West Ext 1 | 17-Aug-14 |
CANCELLATION No acceptable bids |
Karabo Ledwaba | PS-WMS 56/2015 | Consultant for the management of de-listed waste streams at the Rietfontein (GLB+) landfill site until 30 June 2018 | 17-Aug-15 |
CANCELLATION No acceptable bids |
Dalen Schroeder |
A-EE 15/2014 |
Appointment of an electrical contractor for the repair and maintenance of street, area and sports field lighting (excluding Germiston and Benoni for items covered by the existing contracts) on an as-and-when required basis from date of award until 30 June 2017 SUBJECT to maximum contract amount of 30 June 2017 whichever comes firs | 17-Aug-15 | Mokgoshi Electrical CC |
Dalen Schroeder |
A-EE 15/2014 |
Appointment of an electrical contractor for the repair and maintenance of street, area and sports field lighting (excluding Germiston and Benoni for items covered by the existing contracts) on an as-and-when required basis from date of award until 30 June 2017 SUBJECT to maximum contract amount of 30 June 2017 whichever comes first >R10 m recommended to EAC – not approved and re-submitted 17 Aug 2015 Recommended to EAC |
17-Aug-15 | Ampcor Khanyise CC |
Dalen Schroeder |
A-EE 15/2014 |
Appointment of an electrical contractor for the repair and maintenance of street, area and sports field lighting (excluding Germiston and Benoni for items covered by the existing contracts) on an as-and-when required basis from date of award until 30 June 2017 SUBJECT to maximum contract amount of 30 June 2017 whichever comes first >R10 m recommended to EAC – not approved and re-submitted 17 Aug 2015 Recommended to EAC |
17-Aug-15 | Umzantsi Africa Electrical (Pty) Ltd |
Dalen Schroeder |
A-EE 15/2014 |
Appointment of an electrical contractor for the repair and maintenance of street, area and sports field lighting (excluding Germiston and Benoni for items covered by the existing contracts) on an as-and-when required basis from date of award until 30 June 2017 SUBJECT to maximum contract amount of 30 June 2017 whichever comes first >R10 m recommended to EAC – not approved and re-submitted 17 Aug 2015 Recommended to EAC |
17-Aug-15 | Bash Electrical Contractos CC |
Jaco Burger | A-RE 15/2015 | Supply, delivery of various types of animal food – as and when – until 30 June 2018 | 17-Aug-15 | Nyamatsame Trading and Projects (Pty) Ltd |
Jaco Burger | A-RE 15/2015 | Supply, delivery of various types of animal food – as and when – until 30 June 2018 | 17-Aug-15 | Heisie Trading and Projects CC |
Jaco Burger | A-RE 15/2015 | Supply, delivery of various types of animal food – as and when – until 30 June 2018 | 17-Aug-15 | Nexor 527 CC |
Jaco Burger | A-RE 15/2015 | Supply, delivery of various types of animal food – as and when – until 30 June 2018 | 17-Aug-15 | Mokgongoa Agriculture Gardening Enterprise CC |
Jaco Burger | A-RE 15/2015 | Supply, delivery of various types of animal food – as and when – until 30 June 2018 | 17-Aug-15 | Themba Bricks and Steel CC |
Jaco Burger | A-RE 15/2015 | Supply, delivery of various types of animal food – as and when – until 30 June 2018 | 17-Aug-15 | Isikhalo Trading Enterprise 52 CC |
Jaco Burger | A-RE 15/2015 | Supply, delivery of various types of animal food – as and when – until 30 June 2018 | 17-Aug-15 | TMM Select CC |
Jaco Burger | A-RE 15/2015 | Supply, delivery of various types of animal food – as and when – until 30 June 2018 | 17-Aug-15 | Faithrich Trading and Projects CC |
Jaco Burger | A-RE 15/2015 | Supply, delivery of various types of animal food – as and when – until 30 June 2018 | 17-Aug-15 | Gilonka Tehcnologies and Projects CC |
Jaco Burger | A-RE 15/2015 | Supply, delivery of various types of animal food – as and when – until 30 June 2018 | 17-Aug-15 | Grasir Cleaning and Projects CC |
Fumani Shirilele | PS-WMS 41/2015 | Appointment of registered civil engineering consultant to render technical advisory service at the five operational landfill sites until 30 June 2018 | 17-Aug-15 | Anderson Vogt Consulting CC |
Wynand Pretorius Ryk de Beer |
A-DEMS 18/2014 |
Supply, delivery, installation and commissioning of on board navigational systems in various ambulances and fire engines – as and when until 30 June 2017 |
24-Aug-14 | Leobu Morero Trading CC |
Ryk de Beer | PS-DEMS 31/2015 |
Architects and a professional team to render a full professional service for the construction of a fire station in Elandsfontein Isando |
24-Aug-15 | CSM Consulting Services (Pty) Ltd |
Ryk de Beer | PS-DEMS 34/2015 |
Architects and a professional team to render a full professional service for the construction of a fire station in Katlehong |
24-Aug-15 | CSM Consulting Services (Pty) Ltd |
Jabu Dhladhla | PS-EMPD 14/2015 |
Architects and a professional team to render a full professional service for the refurbishment of the establishment of a new precinct station in Kempton Park |
24-Aug-15 |
NON AWARD Fair administrative processes not followed |
Fumani Shirilele | WMS 01/2014 |
Construction of storm water and leachate management systems at Weltevreden Landfill site TERMINATION OF CONTRACT |
24-Aug-15 |
Thusanang Gast (Pty) Ltd TERMINATION OF CONTRACT |
Moloko Mosohli | AS 08/2015 | Supply, delivery and off-loading of toilet paper, paper towels and tissue – as and when – until 30 June 2017 | 24-Aug-15 | Mvunelwa Trading and Projects (Pty) Ltd |
Moloko Mosohli | AS 08/2015 | Supply, delivery and off-loading of toilet paper, paper towels and tissue – as and when – until 30 June 2017 | 24-Aug-15 | Wabex Innovative Technologies (Pty) Ltd |
Moloko Mosohli | AS 08/2015 | Supply, delivery and off-loading of toilet paper, paper towels and tissue – as and when – until 30 June 2017 | 24-Aug-15 | Val Buss Trading and Projects (Pty) Ltd |
Moloko Mosohli | AS 08/2015 | Supply, delivery and off-loading of toilet paper, paper towels and tissue – as and when – until 30 June 2017 | 24-Aug-15 | Marble Arch Trading CC |
Moloko Mosohli | AS 08/2015 | Supply, delivery and off-loading of toilet paper, paper towels and tissue – as and when – until 30 June 2017 | 24-Aug-15 | Duvha Letsatsi Projects and Service |
Moloko Mosohli | AS 08/2015 | Supply, delivery and off-loading of toilet paper, paper towels and tissue – as and when – until 30 June 2017 | 24-Aug-15 | HM Eyethu Construction and Plant Hire CC |
Moloko Mosohli | AS 08/2015 | Supply, delivery and off-loading of toilet paper, paper towels and tissue – as and when – until 30 June 2017 | 24-Aug-15 | Emzanzi Mthemby Cleaning and Distribution CC |
Moloko Mosohli | AS 08/2015 | Supply, delivery and off-loading of toilet paper, paper towels and tissue – as and when – until 30 June 2017 | 24-Aug-15 | Shosho Industrial Suppliers CC |
Ryk de Beer | PS-DEMS 36/2015 |
Architects and a professional team to render a full professional service for the refurbishment of the auditorium of the DEMS Headquarters |
31-Aug-15 | SRSQS Quantity Surveyors |
April Dlamini | EE 01/2015 | Appointment of a suitable and qualified service provider to perform street light audit across EMM | 31-Aug-15 | Vela General Trading CC |
Siphiwe Dube | A-WS 06/2015 |
Unblocking, installation and minor repairs to sewer pipelines for the North-East District – as and when until 30 June 2018. Kempton Park, Tembisa, Benoni |
31-Aug-15 | Lucazi Civil CC |
Siphiwe Dube | A-WS 06/2015 |
Unblocking, installation and minor repairs to sewer pipelines for the North-East District – as and when until 30 June 2018. Brakpan, Nigel |
31-Aug-15 | DKPB Construction CC |
Siphiwe Dube | A-WS 07/2015 |
Cleaning and major repairs to sewer pipelines for the North-East District – as and when – until 30 June 2018 Kempton Park, Tembisa, Benoni. |
31-Aug-15 | Aluwani Nothe Construction and Projects CC |
Siphiwe Dube | A-WS 07/2015 |
Cleaning and major repairs to sewer pipelines for the North-East District – as and when – until 30 June 2018 Brakpan; |
31-Aug-15 | Trenchless Technologies CC |
Siphiwe Dube | A-WS 07/2015 |
Cleaning and major repairs to sewer pipelines for the North-East District – as and when – until 30 June 2018 Nigel. |
31-Aug-15 | Letswamotse Civil Engineering CC |
Siphiwe Dube | A-WS 08/2015 | Contractors for minor installation, repair, maintenance and ancillary work on water network of the North-East district – as and when – until 30 June 2018 Brakpan, Nigel, Benoni | 31-Aug-15 | Aluwani Nothe Construction & Projects CC |
Siphiwe Dube | A-WS 08/2015 | Contractors for minor installation, repair, maintenance and ancillary work on water network of the North-East district – as and when – until 30 June 2018 Kempton Park; Tembisa | 31-Aug-15 | DKPB Construction CC |
Siphiwe Dube | A-WS 09/2015 |
Minor installation, repair, maintenance and ancillary work on water network of the South-West District – as and when – until 30 June 2018 |
31-Aug-15 | Sohlangana Trading 241 CC |
Siphiwe Dube | A-WS 09/2015 |
Minor installation, repair, maintenance and ancillary work on water network of the South-West District – as and when – until 30 June 2018 |
31-Aug-15 | Aluwani Nothe Construction and Projects CC |
Siphiwe Dube | A-WS 09/2015 |
Minor installation, repair, maintenance and ancillary work on water network of the South-West District – as and when – until 30 June 2018 |
31-Aug-15 | Lucazi Civil t/a Licasi Civil CC |
Siphiwe Dube | A-WS 11/2015 |
Major installation, repair, maintenance and ancillary work on bulk water network of the South-West district as and when – until 30 June 2018 Germiston, Vosloorus, Edenvale. |
31-Aug-15 | Aluwani Nothe Construction and Projects CC |
Siphiwe Dube | A-WS 11/2015 |
Major installation, repair, maintenance and ancillary work on bulk water network of the South-West district as and when – until 30 June 2018 Alberton; |
31-Aug-15 | Qubekela Projects CC |
Siphiwe Dube | A-WS 12/2015 |
Major installation, repair, maintenance and ancillary work on bulk water network of the North-East district as and when – until 30 June 2018Kempton Park, Tembisa, Benoni. |
31-Aug-15 | Lucazi Civil t/a Lucasi Civil CC |
Siphiwe Dube | A-WS 12/2015 |
Major installation, repair, maintenance and ancillary work on bulk water network of the North-East district as and when – until 30 June 2018 Brakpan & Nigel. |
31-Aug-15 | Qubekela Projects CC |
Siphiwe Dube | A-WS 13/2015 |
Unblocking, installation and minor repairs to sewer pipelines for the South-West District – as and when – until 30 June 2018 Germiston, Edenvale, Vosloorus. |
31-Aug-15 | Aluwani Nothe Construction and Projects CC |
Siphiwe Dube | A-WS 13/2015 |
Unblocking, installation and micro repairs to sewer pipelines for the South-West District – as and when – until 30 June 2018 Alberton |
31-Aug-15 | Lucazi Civil t/a Lucasi Civil CC |
Brain Whistler | A-WS 05/2015 |
Supply, delivery and off-loading of various sized of water meters, fire hydrants and other related material and appurtenance – as and when – until 30 June 2017 |
3-Aug-15 | NZK Footprint Engineering CC |
Brain Whistler | A-WS 05/2015 |
Supply, delivery and off-loading of various sized of water meters, fire hydrants and other related material and appurtenance – as and when – until 30 June 2017 |
3-Aug-15 | Nala Trading Enterprise CC |
Brain Whistler | A-WS 05/2015 |
Supply, delivery and off-loading of various sized of water meters, fire hydrants and other related material and appurtenance – as and when – until 30 June 2017 |
3-Aug-15 | Methorn CC |
Brain Whistler | A-WS 05/2015 |
Supply, delivery and off-loading of various sized of water meters, fire hydrants and other related material and appurtenance – as and when – until 30 June 2017 |
3-Aug-15 | Davis & Deale Irrigation (Pty) Ltd |
Brain Whistler | A-WS 05/2015 |
Supply, delivery and off-loading of various sized of water meters, fire hydrants and other related material and appurtenance – as and when – until 30 June 2017 |
3-Aug-15 | Sensus South Africa (Pty) Ltd |
Brain Whistler | A-WS 05/2015 |
Supply, delivery and off-loading of various sized of water meters, fire hydrants and other related material and appurtenance – as and when – until 30 June 2017 |
3-Aug-15 | Mosa Lesareng Trading and Projects CC |
Mandla Mthimkhule | WS 02/2014 |
Re-instatementof contract for the upgrading of Welgedacht bulk water supply from Prewsida Reservoir – Phase 1 |
6-Jul-15 | ZM and Nikiwinono Construction CC |
PROJECT MANAGER |
CONTRACT NO | DESCRIPTION OF BIDS AWARDED FOR THE MONTH OF SEPTEMBER 2015 |
DATE SERVED AT BAC |
SUPPLIER |
Laid-law Mnyakeni | PS-F 18/2015 | Appointment of a finance meter management consultant to manage the EMM water and electricity meter reading and credit control process from date of award until 30 June 2017 | 3-Aug-15 | Boffin & Fundi (Pty) Ltd |
Laid-law Mnyakeni | PS-F 18/2015 | Appointment of a finance meter management consultant to manage the EMM water and electricity meter reading and credit control process from date of award until 30 June 2017 | 3-Aug-15 | Aurecon South Africa (Pty) Ltd |
Lianne de Witt | A-ICT 11/2015 |
Multiple contractors for the supply, installation and maintenance of wireless network infrastructure – as and when – until 30 June 2018 |
14-Sep-15 | iMAX Wireless CC |
Ryk de Beer Ryno v Vuren |
Paragraph 32 |
RT4-2015ME; Supply and delivery of ambulance-rescue-emergency equipment and accessories – as and when until 28 February 2017 |
Panel to be reported on a monthy basis | |
Mohamed Karanie | AF 01/2015 |
Appointment of a banker to supply banking services and/or an independent service provider/s to supply cash handling collection, management and handling related services date of award until 30 June 2018 |
24-Aug-15 | Nedbank Linited |
Mohamed Karanie | AF 01/2015 |
Appointment of a banker to supply banking services and/or an independent service provider/s to supply cash handling collection, management and handling related services date of award until 30 June 2018 |
24-Aug-15 | Absa Bank |
Mohamed Karanie | AF 01/2015 |
Appointment of a banker to supply banking services and/or an independent service provider/s to supply cash handling collection, management and handling related services date of award until 30 June 2018 |
24-Aug-15 | Standard Bank of South Africa Limited |
Philip du Plessis Kulani Mayayise |
PS-PT 09/2015 | Professional service providers for the planning, design and supervision of transport related projects as and when – until 30 June 2017 | 17-Aug-15 | Gibb (Pty) Ltd |
Philip du Plessis Kulani Mayayise |
PS-PT 09/2015 | Professional service providers for the planning, design and supervision of transport related projects as and when – until 30 June 2017 | 17-Aug-15 | PH Bagale (Pty) Ltd |
Thengo Qokoyi | Section 32 | Panel of contractors for the construction of various roads and stormwater systems. | 31-Aug-15 | Panel of suppliers |
Liaane de Witt | A-ICT 08/2015 | Provision and maintenance of existing optic fibre infrastructure – as and when – until 30 June 2017 – SUBJECT TO CAPPED AMOUNT OR 30 June 2017 whichever comes first | 25-Mar-15 | Dark Fibre Africa (RF) (Pty) Ltd |
Mary Lekgau | A-DEMS 19/2014 |
Appointment of an accredited service provider to provide the following training (1) Fire Investigation (2) Fire Prevention (3) Advanced Fire Prevention – as and when – until 30 June 2017 – |
7-Sep-15 |
CANCELLED All bids exceed R1 m – 80/20 advertised |
Mabeana Matjokotja | A-EE 14/2014 | Supply, delivery and off-loading of ring main units (RMU) – as and when – until 30 June 2017 | 7-Sep-15 |
CANCELLED Spesifications does not meet SANS 1874 requirements |
Alfred Sidia | A-RS 10/2015 | Replacement and maintenance of traffic signal equipment for the Eastern area – as and when – until 30 June 2018 | 7-Sep-15 |
CANCELLED No acceptable bids |
Liaane de Wit | A-ICT 07/2015 | Multiple service providers for the removal of redundant damaged aerial fibre – as and when – until 30 June 2017 | 14-Sep-15 | Specialized Access Services CC |
Gothitile Project Management CC | Gothitile Project Management CC | Gothitile Project Management CC | Gothitile Project Management CC | Gothitile Project Management CC |